- The squad garage is ready and waiting to be inspected on Monday and poured on Tuesday.
- The detention doors are installed and the block has been filled and primed for paint. We are starting to clear out the areas where epoxy flooring will be installed.
- The seat walls at the front of the building are complete with the specialty lights installed.
- The upstairs painting is almost complete and border ceiling tiles dropped with almost all of the light fixtures in.